Classes begin inside new UW-Madison chemistry building

Students returning to class for the spring semester last week at the University of Wisconsin-Madison were greeted with a new academic building at the heart of campus.

Inside UW-Madison’s new Chemistry Tower: modern labs, study spaces and a ‘library of the future’

Goodbye, crowded chemistry labs. So long to space crunches so severe that some 20% of UW-Madison students took introductory organic chemistry at a different university.

UW-Madison opened its gleaming nine-story Chemistry Tower to students this semester after months of construction delays. The new building at 1101 University Ave. will ease enrollment bottlenecks that have plagued the department for decades.

Construction Update 08/24/2020

New Tower. There is lots of activity on the tower rooftop where curbs are being set around the periphery and roofing is being installed to prevent incursion of water. In the sub-basement and fifth floor plasterboard drywall is being installed. This has had to wait until now because drywall and dampness are a bad combination. …

Construction Update 07/27/2020

Fire Protection. Fire protection work is going on in both Shain and Mathews first floors this week. Because of the work in Shain, the main entrance to Shain tower is closed all this week. Please enter the chemistry complex at the basement level, Daniels building, along Johnson Street.  Your key will work in the lock …

Construction Update 07/20/2020

New Tower. There is more to see in the new tower, from sub-basement to ninth-floor mechanical penthouse. Upper floors of the tower continue to be built out, with studs installed for walls from the fifth through eighth floors. There is more ventilation ducting and electrical work on all floors as well. In the sub-basement, both …

Construction Update 07/13/2020

A Walk Around the Chemistry Block. From almost every angle the exterior appearance of the chemistry-building complex has been altered by the construction project. From the south, Daniels has been extended upward by the huge ventilation duct that runs around the periphery of the roof. On the east side there are changes from sub-basement to …

Construction Update 05/11/2020

This week’s presentation at the department meeting chronicled progress on several projects the Facilities Committee has overseen. It provides a visual tour of the new chemistry tower from the sub-basement up to the ninth-floor mechanical space. Here is a link to the presentation: 05112020 Building Update

Construction Update 04/20/2020

New Tower. The second big concrete pour on the ninth floor happened last Thursday, so all floors are now in place. The ninth floor is partly roof and partly mechanical space. The mechanical space will house large air handlers, stacked two or three high, that will condition air supplied to the new tower and to …

Construction Update 04/13/2020

New Tower. In the sub-basement the large lecture rooms are taking shape with concrete poured for some of the tiers of seats. Shoring is in place for the lower part of the monumental staircase that will enable access to the lecture rooms, though the steps themselves have not yet been poured. Last week, at the …

Construction Update 04/06/2020

New Tower. Work in the new tower continues. The remaining concrete for the eighth floor was poured last week and the west side of the ninth floor (mechanical area and roof) is ready for concrete to be poured this week. The temporary stairway that enables workers to access upper floors without using ladders has been …