Construction Update 11/19/2018

Progress has been made on construction of the permanent concrete masonry wall that will separate the north end of Daniels from demolition and construction. The wall, which will be permanent, will be waterproofed and insulated. Once it is complete the tempera­tures in the corridors at the north ends of the first and second floors should …

Construction Update 11/12/2018

The heated restroom trailer outside the south exits from Daniels basement is now in operation. This clean, warm trailer is for UW–Madison students, staff, and faculty, to avoid crowding in the restrooms inside Daniels. It is not for use by construction personnel. As the photos below show, our building is sur­rounded by construction zones on …

Construction Update 11/5/2018

These weekly construction updates are now available directly from the home page of the department website as well as appearing in the department newsletter and its online archive (http://chem.wisc.edu/newsletter). You can go directly to the construction updates at this URL: https://badgerchemist.chem.wisc.edu/weekly-updates/. Last Thursday afternoon the large restrooms at the north end of the first floor …

Construction Update 10/29/2018

Today (Monday, October 29) occupants of Shain Tower are asked to be on a  fire watch’: the fire sprinkler system will not be operable. Consider postponing any particularly hazardous procedures and be alert for fires. This is a consequence of repair of a water main that serves Shain tower. Water supply to labs, restrooms, etc. in …

Alumni in the News: 5 Favorite Things: Tanya Knickerbocker, Yakima, chemistry professor

Tanya Knickerbocker, who teaches chemistry at Yakima Valley College, was recently featured in the Yakima Herald. Read the article here: https://www.yakimaherald.com/lifestyle/favorite-things-tanya-knickerbocker-yakima-chemistry-professor/article_fd908ea0-d3f7-11e8-977f-5bb9a41232cb.html

Construction Update 10/22/2018

During the next couple of weeks, with very short notice of the exact date and time, we expect natural gas service to Daniels and Mathews wings to be shut off for up to half a day. If you use natural gas piped into the labs in either Daniels or Mathews, please tell John Moore (jwmoore@chem.wisc.edu) as soon …

Construction Update 10/15/2018

In the north ends of Daniels floors B, 1 and 2, much work has been completed in preparation for constructing the new,permanent masonry wall that will separate our building from the demolition zone. We expect construction of the separating wall will begin on the second floor of Daniels next week. The wall is being built from …

Construction Update 10/08/2018

Good news! This week we expect construction to begin on the new, permanent masonry wall that will separate our building from the demolition zone. The plan is to begin on the second floor of Daniels and work down floor by floor. Once the wall is complete there should be less noise in the north end of Daniels …

Addressing our biggest challenges — and mysteries — at the Wisconsin Science Festival

By University Communications Among the hundreds of events offered around the state during the Wisconsin Science Festival, which runs Oct. 11 – 14, are four in-depth discussions in Madison on some of the most significant challenges science is addressing — and universal questions science is answering. Climate change and the ‘Anthropocene’ Two series of events will address …

New fuel cell concept brings biological design to better electricity generation

By Mark E. Griffin Communications Specialist at the Wisconsin Energy Institute Fuel cells have long been viewed as a promising power source. These devices, invented in the 1830s, generate electricity directly from chemicals, such as hydrogen and oxygen, and produce only water vapor as emissions. But most fuel cells are too expensive, inefficient, or both. In …